Friday 7/20: Beams being excavated. Steel cages being assembled. Dumpster arriving.
Friday 7/27: Pouring 50 yards of concrete for exterior beams. Perfect weather for concrete.
Forms came off Wednesday. Rough grade Friday. CMU starts Monday.
8/7-9: Interior drainage completed. Concrete debris picked up. Crawlspace rough grade. Begin CMU (which is those concrete blocks).
8/10: Crawlspace drainage. CMU started 4 rows lift.
8/13 CMU walls being filled with grout.
I got the app TimeShutter, which helps guide you in taking a picture of exactly the same thing from the same vantage point. That will help make sharing progress easier, I’m sure.