House update #20

Mainly because the floors are going to take 3+ days to stain/cover/dry, we changed our move date 7 days. November 1, ladies and gents, is the big day.

Thursday 10/10: laundry pass-thru, place mailbox, driveway gate location, documents for flood insurance, audio visual system begging to get trimmed out, gutters getting installed, more tile backsplash, plumbers putting in faucets, painters working, Madeval adjusting kitchen cabinets for appliances

Thursday 10/10
Thursday 10/10
I built the hamper so they could do a cutout on the other side

Friday 10/11: style of outlet covers, exterior light trim kit, select artificial grass, locations for usb-c outlets, place master barn door handles, lots of electricians – can lighting going in

Friday 10/11
Master bath tub is in!!! I LOVE IT.
master bedroom tv nook finished
can lighting and speaker trim
Meeting with gate company about railings
pavers in place

Saturday, 10/12: gutter install, decking in backyard, painting continues, more electric and plumbing, mailbox in place

Front view as of weekend
This sliding door was accidentally painted blue like our doors but now is black
Raised lower deck platform
Cali Bamboo going on top of deck platform
Media rack being built. This houses controls for all tvs, speakers, internet, the alarm system, etc.
Trufig outlet will allow for the backsplash to be continuous… you’ll see

Monday, 10/14: Meeting with landscaper to decide lighting, oak tree placement, final garden design and plants. It is going to be so amazing – I’m excited. The representative delivering the oak tree laughed at me that she should bring it on Saturday. She said we’d never be ready.

Worker vehicles line the street! Today we have irrigation, landscaping, plumbing, painters, electricians, and audio/visual
Upper deck in process
Upper deck
Back lower deck
Lower deck
sanding the floors
Master bath shower head is in!
Master bath

Tuesday, 10/15: Selected floor stain

The blue X is the winner
Stairs
Firepit installed
Downspouts
I can’t believe the bed is already cleaned, irrigation is finished, and soil is ready for planting … in one day!

Wednesday, 10/16: Mr. B spent time with the cable guys. I was away all day and went over around 4pm to see downstairs lighting being installed. Holy smokes! I was blown away.

Front porch
Garage is white!!! Still to stain window trim and replace lights
Fruit trees relocated to the side
This guy is digging plumbing to connect the room over the garage to the water line
Porch ceiling stain
And also for craft room doors
Entry floor lighting – very cool
Stairs stained. Working on second floor.
Installing my 5 globe pendants
My office
Powder bath
Living room light – I might have squealed. It’s stunning. I bought this fixture first of all of them… over a year ago now.
LOVE IT!
Related Posts Plugin for WordPress, Blogger...
This entry was posted in Home and tagged , , . Bookmark the permalink.

One Response to House update #20

  1. Those lights are awesome! I know I’ve said this before, but your new house is such a work of art, very impressive. It’s going to be so exciting to move in.